Samaya Group Company Ltd. built the Tabuk 380 kV double-circuit overhead transmission line for Saudi Electricity Company under an engineering, procurement and construction contract, beginning in March 2020 and completing commissioning on 24 March 2022. The line runs approximately 112.5 kilometres across the Tabuk region of northwestern Saudi Arabia and carries two 380 kV circuits into the country's Northern Grid.
A transmission line begins long before steel appears above the ground.
For the Tabuk project, the first task was to turn a proposed route into 309 buildable tower positions. Each location had to be surveyed, investigated and connected to the construction programme before excavation, foundation work or tower erection could begin.
Samaya Group's responsibility extended from route engineering and material procurement to civil works, installation, testing and final commissioning. The completed line includes the conductors, grounding, fibre-optic communications and protection systems required to operate as part of the Northern Grid.
The contract Saudi Electricity Company awarded
Saudi Electricity Company awarded the Tabuk 380 kV overhead transmission line to Samaya Group Company Ltd. as an engineering, procurement and construction contract, with the letter of award issued in March 2020 and a contract duration of twenty-four months from commencement.
The line was specified as part of Saudi Electricity Company’s National Grid Reinforcement Programme. Its purpose was to raise the reliability, stability and transmission capacity of the high-voltage network in the north-west by interconnecting key substations within the Northern Grid, and to support growing electricity demand in the Tabuk region.
Under an EPC arrangement the contractor carries the whole chain: design to SEC standards and international codes, procurement of every tower, conductor and fitting, all civil and erection works, and testing through to energisation. That is why a single company appears against scopes as different as geotechnical investigation and fibre-optic commissioning.
Turning a route into 309 construction sites
A transmission corridor may appear continuous on a map, but it is built as a series of individual sites.
The Tabuk route was surveyed over approximately 113 kilometres before the final 112.5-kilometre alignment was established. Engineers had to account for elevation, ground conditions, route direction, access, electrical clearances and the roads, utilities and existing lines that the new corridor would encounter.
Those decisions determined where each tower would stand and what type of structure would be required. A tower on a straight section carries a different set of forces from one placed at a major turn in the route. Ground conditions can also change from one position to the next, affecting excavation, reinforcement and foundation design.
Route planning therefore influenced far more than the appearance of the finished line. It affected material quantities, access requirements, crossing locations, tower types and the order in which construction could proceed.
By the time the alignment was approved, the project had become 309 separate engineering and logistical tasks connected by one programme.
Access before excavation
No tower position can progress until crews and equipment can reach it.
The Tabuk project included more than 56 kilometres of access-road grading, together with drainage and culvert works along the corridor. These routes allowed excavators, concrete vehicles, cranes, tower components and conductor-stringing equipment to move between construction locations.
Access work is not usually visible in photographs of a completed transmission line, but it can control the pace of the entire project. If a tower location cannot be reached, excavation cannot begin. If the foundation is delayed, tower erection must wait. If one structure remains incomplete, conductor stringing may be interrupted across several adjoining spans.
This makes logistics part of the engineering problem. Across a route longer than 100 kilometres, progress depends on keeping multiple work fronts active while preserving the sequence each section requires.
The foundations beneath the line
The civil scope included approximately 4,582 cubic metres of foundation concrete and more than 700 tonnes of reinforcement steel. Most of that material is now below ground.
At each tower position, crews had to excavate the site, install reinforcement and set the tower-base components accurately before concrete was placed. The foundations then needed enough time to gain strength before the steel structures could be erected.
Accuracy at this stage was essential. A small positioning error at the base becomes more difficult to correct as a lattice tower rises. The foundations also have to carry the weight of the structure, withstand conductor tension and resist the forces created by wind and operating conditions.
The towers dominate the completed landscape, but their stability depends on civil work that is largely hidden from view.
Six tower types for one transmission corridor
The 309 towers were selected according to their positions and functions along the route.
| Tower type | Quantity |
|---|---|
| Suspension towers | 206 |
| Small-angle towers | 33 |
| Medium-angle towers | 23 |
| Heavy-angle towers | 19 |
| Transposition towers | 19 |
| Dead-end or terminal towers | 9 |
Suspension towers formed most of the corridor, carrying conductors through relatively straight sections. Angle towers were used where the line changed direction; the greater the turn, the greater the forces transferred to the tower and its foundation. Dead-end towers anchored the conductor system at terminal points and other locations where the full line tension had to be restrained.
The 19 transposition towers served a different purpose. A transposition tower is a structure that changes the relative positions of the three phases along a transmission route. Over a long three-phase line each phase may otherwise occupy a different physical position relative to the others, creating small differences in electrical impedance. Rotating the phases balances those characteristics across the complete line.
It is a feature most people would never notice from the ground, but it contributes directly to the line’s performance.
More than 2,700 kilometres of conductor
Once a continuous section of towers had been erected and inspected, conductor installation could begin.
The Tabuk line uses a double-circuit, quad-bundle configuration. A quad bundle means each of the three phases in a circuit is carried by four sub-conductors rather than one, which reduces electrical losses and corona at 380 kV. Across the route, the scheduled phase-conductor quantity was approximately 2,781 kilometres.
The conductors had to be pulled through successive spans under controlled tension. Their final sag and position had to remain within design limits while maintaining safe clearances from roads, utilities, existing lines and the ground below.
The completed conductor system also relied on thousands of smaller components:
insulator assemblies
clamps and connection fittings
armour rods
spacer dampers
vibration dampers
grounding and lightning-protection equipment
Spacer dampers maintain the correct separation between the four sub-conductors in each bundle. Vibration dampers reduce repeated wind-driven movement that could damage conductor strands and fittings over time. These components are far smaller than the towers, but the line’s long-term reliability depends on them.
Thirty-four crossings along the route
The Tabuk transmission corridor crossed 17 roads, 11 utility and service corridors and six existing electrical lines or other special locations. Each of those 34 crossings required additional planning.
Work above a road may need traffic management and temporary protection. Utility crossings must preserve safe separation from existing services. Work around an operational electrical line may depend on agreed procedures and limited outage periods.
Crossings can therefore exert far more pressure on a project than their physical length suggests. The construction team may be ready, but work cannot proceed until permissions, access arrangements and protection measures are in place. A delay at one crossing can interrupt conductor stringing and testing across a much larger section of the route.
For a linear project, managing the places where the new line meets existing infrastructure is as important as building the open sections between them.
Fibre-optic communications above the line
The Tabuk project was designed to carry both electricity and operational data.
Approximately 116 kilometres of Optical Ground Wire, known as OPGW, were installed above the phase conductors, alongside a similar length of conventional earthwire. OPGW is a cable that serves two functions at once: its outer structure helps shield the line from direct lightning strikes, while fibre-optic strands inside it carry protection, control and communication data between different parts of the transmission network.
Those fibre links support line monitoring, fault detection and the rapid exchange of protection signals. A transmission line must not only carry electricity; it must also be monitored and controlled as part of the wider grid. The Tabuk corridor therefore operates as both a power connection and a communications route.
What Samaya Group delivered
Samaya Group Company Ltd. was responsible for delivering the Tabuk 380 kV double-circuit transmission project from engineering through commissioning. Its scope included:
route studies and detailed engineering
material procurement
access and civil works
foundation construction
tower supply and erection
conductor and insulator installation
grounding and lightning protection
OPGW and fibre-optic communications
testing and final grid integration
That work required coordination across several disciplines. Survey and engineering teams established the route. Civil crews prepared access and foundations. Structural teams erected six categories of towers. Electrical specialists installed conductors, insulators and line hardware. Telecommunications engineers completed the fibre-optic links. Quality, safety and commissioning teams then verified the completed system.
Each discipline delivered one part of the project, but none could operate independently. The line could enter service only after all its structural, electrical and communication components had been brought together and tested as one system.
From mechanical completion to commissioning
A completed corridor of towers and conductors is not yet an operating transmission asset.
The structures and fittings had to be inspected. Conductors, insulators and grounding systems required electrical testing. Fibre-optic connections and protection equipment had to exchange information correctly across the route.
Mechanical completion was reached on 24 February 2022. Final commissioning followed on 24 March 2022, bringing the Tabuk 380 kV double-circuit transmission line into Saudi Electricity Company's Northern Grid.
That final stage changed the project from a collection of individual foundations, towers, conductors and communication systems into one functioning high-voltage connection.
What the Tabuk project demonstrates
The principal figures describe the scale of the project: approximately 112.5 kilometres of completed route, 309 tower positions, six tower categories, more than 2,700 kilometres of phase conductor, approximately 116 kilometres of OPGW, and 34 road, utility and special crossings.
The figures do not fully describe the delivery challenge. The project depended on the accuracy of the route, the availability of access, the quality of the foundations, the sequence of tower erection, the management of crossings and the integration of electrical and communication systems across a widely distributed construction programme.
Each stage created the conditions required for the next.
The towers are the most visible result of the Tabuk transmission project. The more significant result is that 309 separate structures and their supporting systems were completed as one operating part of Saudi Arabia’s high-voltage transmission network.
| Item | Detail |
|---|---|
| Project | Tabuk 380 kV double-circuit overhead transmission line |
| Contractor | Samaya Group Company Ltd. |
| Client | Saudi Electricity Company |
| Location | Tabuk Region, Saudi Arabia |
| Completed route length | Approximately 112.5 kilometres |
| Surveyed alignment | Approximately 113 kilometres |
| Tower positions | 309 |
| Voltage | 380 kV |
| Delivery model | Engineering, procurement and construction |
| Project period | March 2020 to March 2022 |
| Mechanical completion | 24 February 2022 |
| Final commissioning | 24 March 2022 |



